Jamku HelpJamku Help
Getting Started
Guide
Changes
Blog
API
Jamku App
Getting Started
Guide
Changes
Blog
API
Jamku App
  • 2026 April
  • 2026 March
  • 2026 Feb
  • 2026 Jan
  • 2025 Dec
  • 2025 Nov
  • 2025 Oct
  • 2025 Sept
  • 2025 August
  • 2025 July
  • 2025 June
  • 2025 May
  • 2025 April
  • 2025 March
  • 2025 February
  • 2025 January
  • 2024 December
  • 2024 November
  • 2024 October
  • 2024 September
  • 2024 August
  • 2024 July
  • 2024 June
  • 2024 May
  • 2024 April
  • 2024 March
  • 2024 February
  • 2024 January
  • 2023 December
  • 2023 November
  • 2023 October
  • 2023 September
  • 2023 August
  • 2023 June
  • 2023 May
  • 2023 April
  • 2023 March
  • 2023 February
  • 2024 June
  • 2024 May
  • 2024 April
  • 2024 March
  • 2023 January
  • 2022 December
  • 2022 November
  • 2022 October
  • 2022 September
  • 2022 August
  • 2022 July
  • 2022 June
  • 2022 May
  • 2022 April
  • 2022 March
  • 2022 February
  • 2022 January
  • 2021 December
  • 2021 November
  • 2021 October
  • 2021 September
  • 2021 August
  • 2021 July
  • 2021 June
  • 2021 May
  • 2021 April
  • 2021 March
  • 2021 February
  • 2021 January
  • 2020 December
  • 2020 November
  • 2020 October
  • 2020 September
  • 2020 August
  • 2020 July
  • 2020 June
  • 2020 May
  • 2020 April
  • 2020 March
  • 2020 February
  • 2020 January
  • 2019 December
  • 2019 November
  • 2019 October
  • 2019 September

2021 December

3.26.2 20 December 2021

To view all the feature requests implemented in this version check out GitHub page. github.com/madrecha/jamku/milestone/49

Improvements

  1. Shift bill print lines up/down on a single click(of arrow icons) in Bill edit page. No more pesky editing of sort number. #829.
  2. Now you can move bill location from client level to group level and vice versa of a particular group by using the Move Location feature in Group View -> Bill Location tab #842.
  3. Now you can edit team and labels in Task List "Table View". For this switch to Edit mode and click on the Task Team or Task label cell of any task in table view. #868. #843.
  4. Improved UI of Task history (aka Task Notification) page. Also now the note type you select get's stored in the browser. So next time you visit this page those options are automatically selected. #867.
  5. Improved the UI of Todo Template View -> Template Items list. It looks same as Task View > Todo tab. #847.
  6. In Work done suggestions page when you select a client, along with going and stuck tasks you will also see today's completed tasks. Also added Work Done Card in this page same as Dashboard page, which will show's today's and yesterday's work done by you. Check out this #856 for background on this feature request.
  7. Task Notes character limit has been increased from 300 to 500 characters. #837.
  8. Now you can remove target date from task in bulk. To do this select the tasks from Task List. Click on Update Task button for bulk update. Under Info tab select Target Date, let the date value be empty and click on the update toggle and then click on Update button. #855.
  9. Todo target date cannot be a past date from today. Only applicable when adding or changing target date. #851.
  10. Following into is shown create time, created by, modified time, modified by; on Receipt Update dialog box and Bill edit page. #854. #853.
  11. Now you can send emails to your team in bulk. Goto Office Config -> Email -> Team Emails tab. Select the team members. Click on Send Email button. Fill the necessary details and then click on Send. #836.

Bug Fixes

  1. By default notes timeline filter in Sub Task View -> Dashboard tab is set to manual notes. #865.

3.26.1 12 December 2021

To view all the feature requests implemented in this version check out GitHub page. github.com/madrecha/jamku/milestone/48

New Target Day in Subtask Template Items.

This feature can help you specify the target date for subtask created using subtask templates. To use this feature follow the steps below.

  1. Visit Office Config -> Subtask Temaplte. Now in the subtask template list click on any subtask template.
  2. Click on the Add button or the Pen icon, a dialog box will appear. You'll see Target Day field in it.

The Target day field works as follows.

  1. To specify the target date for subtask. Add the number of days in Target Day field while creating or updating a subtask template item. The target date will be assigned based on the Target Day value provided and Task Due Date in which this template is added.
  2. To make the Subtask target date same as Task Due date make Target Day as 0.
    For ex: If Task Due date = 12 December 2021, and you've enter 3 in the Target Day field. Then the Subtask target date = 9 December 2021 i.e 3 days before Task's due date.
  3. To assign the Subtask target date after it's respective Task due date assign a negative value to Target Day field.
    For ex: If Task Due date = 12 December 2021, and you've enter -3 in the Target Day field. Then the Subtask target date = 15 December 2021 i.e 3 days after Task's due date.

Improvements

  1. Added Todo Group field while creating/updating todo template items. So groups are now directly assign to todos when added in task through templates.
  2. Now you can also specify Target Date for each todo. #544.
  3. Now the File upload tab in Task View, Client View and Subtask view can only be seen if the feature is activated for your office. #834.
  4. Added link to Task no to route to Task view in work done add dialog box. #824.
  5. Options to copy unique email ids from Client List -> Send Email -> Copy Emails tab. #835.
  6. Improved the font style for serial number in Bill Print preview pages. #839.

Bug Fixes

  1. Fixed the report filter issue while navigating from Home calendar to Task List. #838.

3.26.0 05 December 2021

To view all the feature requests implemented in this version check out GitHub page. github.com/madrecha/jamku/milestone/46

New Bill Move from one client group to another

Now you can move bills and bill Location from one group to another. #369, #665 To know more about the process check this out -> How to move Bills from one client group to another

New Option to disallow task completion if subtask is pending.

Similar to todo config now you can set subtask config as well to allor or dis allow task completion based on pending sub task. To configure this setting, visit Office Config -> Settings tab. #801.

Improvements

  1. On bill view page, to update client location just select the location from the dropdown. It will auto update the client location without the need to click Save or click on "Enable Printing". #821
  2. Bulk import update of shortcut has new fields - linkto, linkid, linkname and isclientvis. Use "Shortcut update" in data import page. #819
  3. Highlighted the count of Pending subtask and hearing in Task view -> Dashboard tab. #801
  4. Navigating to new page will automatically scroll to the top of the page. #828
  5. Entity legal name character legth increased from 50 to 200. #820

Bug Fixes

  1. Bill reset numbering issue has been fixed now. #817.
Last Updated: 20/12/21, 9:35 am
Prev
2022 January
Next
2021 November